In only 9 days, the team on site the 𝐑𝐮𝐧𝐧𝐞𝐦𝐞𝐝𝐞 𝐑𝐨𝐚𝐝 𝐑𝐞𝐬𝐭𝐨𝐫𝐚𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 has made significant strides. Road work is always a beauty to behold and the Runnemede project is no exception.
Thus far, 70 ft. of the roadway was excavated making way for the construction of a 140ft. long retaining wall, of which, 60 ft. of its base has been casted. The team now works on the stem of the wall; the reinforcement of the stem and formwork were fabricated and installed this week.
 
This project promises to bring much relief to residents of Runnemede and motorists traversing the North-Eastern end of the island. Stay tuned for updates!